Removing capital bottlenecks, accelerating progress of resettlement areas serving industrial parks
On the afternoon of August 11, Comrade Vuong Quoc Tuan, Member of the Party Central Executive Committee, Deputy Secretary of the Provincial Party Committee, and Chairman of the Provincial People's Committee, chaired a conference to review the progress in implementing resettlement areas serving site clearance for industrial parks across the province.
Anh-tin-bai

Scene of the Conference

Also attending the conference were Comrades Nguyen Linh, Member of the Provincial Party Standing Committee and Permanent Vice Chairman of the Provincial People's Committee; Tran Van Hau, Vice Chairman of the Provincial People's Committee; and leaders of departments, sectors, and a number of localities.

The province is currently investing in the construction of 12 industrial park projects. To serve site clearance work, the entire province is implementing 30 resettlement projects with a total investment of VND 12,831 billion.

Anh-tin-bai

Comrade Le Kim Phuc, Director of the Department of Finance, reports the capital needs of the resettlement projects

Anh-tin-bai

Leaders of Diem Thuy Commune discussing capital allocation options for the projects

At the conference, delegates focused on assessing implementation progress and the difficulties in allocating and balancing capital, while proposing options for mobilizing lawful capital sources, securing the resources needed to implement the resettlement areas, and meeting the site clearance requirements for industrial parks.

Anh-tin-bai

Chairman of the Provincial People's Committee Vuong Quoc Tuan delivers directive remarks at the conference

Delivering directive remarks at the conference, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee Vuong Quoc Tuan emphasized that, in order to accelerate the pace of investment in industrial parks, the progress of site clearance, including resettlement areas, must first be ensured. Each project must have its tasks, workload, and timeline clearly defined, providing a basis for residents to understand the roadmap, reach consensus, and hand over the site promptly.

The Chairman of the Provincial People's Committee directed departments, sectors, and localities to swiftly review each resettlement project and clearly identify the workload completed, the work remaining, and the capital needs for site clearance and infrastructure investment. On that basis, an approach for handling each project is to be agreed upon, ensuring resources and implementation progress.

Regarding resource mobilization, he assigned the Department of Finance to act as the focal point to study a coordination plan among industrial park infrastructure investors, resettlement area investors, and credit institutions, while ensuring compliance with legal regulations. In particular, it is necessary to clarify the feasibility of enterprises advancing capital and extending loans to support localities in carrying out site clearance and infrastructure investment; and to clearly define the timing of the loans, the loan term, the responsibilities of the parties, and the method of managing, using, and repaying the capital. The plan must ensure the principles of regulatory compliance, transparency, and feasibility, must be capable of immediate implementation for projects currently in need of resources, and must also be studied for application to resettlement areas serving industrial park projects in the coming time.

He assigned Vice Chairman of the Provincial People's Committee Tran Van Hau to personally direct and work with industrial park infrastructure investors in need of site clearance; and to reach agreement on the policy for advancing capital and extending loans to implement the resettlement areas, creating a reserve of site-cleared land to attract secondary investors. The Department of Finance is to coordinate with relevant units to swiftly carry out the assigned tasks and finalize the plan before August 20, 2026, so that the Provincial People's Committee can report to the Provincial Party Standing Committee for review and comment, to serve as the basis for the next steps.

Huong Lan - Thanh Chung
thainguyen.gov.vn
image advertisement

image advertisement image advertisement
Access Statistics
  • Đang online: 1
  • Hôm nay: 1
  • Trong tuần: 1
  • Tất cả: 1

Managing agency: People's Committee of THAI NGUYEN PROVINCE

Copyright (C) 2009-2010 belongs to Thai Nguyen Province People's Committee

Head office: No. 88, Hung Vuong street, Thai Nguyen Email: portal@thainguyen.gov.vn Phone: 0208.3851149 Fax: 0208.3851149

Specify the source "en.thainguyen.gov.vn" when releasing information from this website