Expediting the handover of clear ground for investors to implement projects

In order to further accelerate compensation, resettlement support and enhance security maintenance in project implementation areas as well as timely deliver clear ground to investors for project deployment in the province, the Provincial People's Committee has recently issued an implementation organization plan, assigned specific tasks and established completion deadlines for each type of project.

Delegates performing the groundbreaking ceremony of Song Cong II Industrial Park - Phase 2 Project (photo taken on March 10, 2025)

People's Committees of districts and cities should: Develop detailed plans to implement compensation, support and resettlement for each specific project, clearly defining the responsibilities of each department, sector, unit, locality and investor along with completion deadlines for each task.

Perspective of Yen Binh Industrial Park 3

Specifically, for industrial parks and clusters that already have infrastructure investors, District and City People's Committees must develop compensation, support and resettlement implementation plans before April 20, 2025, ensuring the following schedules:

Song Cong II Industrial Park phase 2: No later than June 30, 2025, Song Cong City People's Committee must clear and hand over approximately 120 hectares (Zone 2) to Viglacera Thai Nguyen Joint Stock Company for project implementation.

Yen Binh 3 Industrial Park: No later than the beginning of the third quarter of 2025, Phu Binh District People's Committee must clear and hand over approximately 40 hectares to BMK Group Joint Stock Company for infrastructure development connecting Yen Binh 3 Industrial Park.

Luong Phu - Tan Duc Industrial Cluster and Tan Duc Industrial Cluster: Before May 19, 2025, Phu Binh District People's Committee must clear and hand over approximately 20 hectares for each industrial cluster to investors for groundbreaking.

Ha Chau Industrial Cluster 1 and Ha Chau Industrial Cluster 2: In the third quarter of 2025, Phu Binh District People's Committee must clear and hand over approximately 20 hectares for each industrial cluster to Thuong Dinh Group Investment and Development Joint Stock Company and Minh Duc Group Investment Joint Stock Company for infrastructure development.

Remaining industrial clusters in the province: District and City People's Committees must develop compensation, support and resettlement plans to provide clear land as soon as possible to investors for project implementation according to schedule.

The People's Committees of districts and cities should develop timeline plans for compensation and resettlement support to be handed over to investors as soon as possible

For infrastructure development projects, residential areas, urban areas and public investment projects: District and City People's Committees must develop timeline plans for compensation and resettlement support as soon as possible to hand over to investors for project implementation according to schedule, with regular reports to the Provincial People's Committee before 16:00 every Friday.

The Provincial People's Committee has also assigned specific tasks to relevant departments and sectors for identifying and resolving difficulties faced by localities; conducting timely appraisals; reviewing and expediting implementation progress; guiding investors in completing documentation and procedures; and definitively resolving complex disputes and negative issues in compensation, support and resettlement work when the State acquires land...